| Getting Electricity connected |
The following is information on how to apply for Electricity connection and the documents required to apply. |
Aydem EDAS - Aydem Elektrik Dagitim A.S. (Aydem Electricity Distribution Inc. Co.) is in charge of Electricity Distribution to the following provinces of Turkey: Denizli, Aydin and Mugla. Aydem EDAS - Address: Yeni Mahalle, 823 Sokak, Didim Tel: (0256) 811 28 41 |
 |
|
Subscription Applications |
Connection Application And Documents Requested |
1 - Connection (Energy Permission) Application; |
Applications must be made by; |
a.) Property owner and / or the owner or representative, |
b.) Tenant, if the property has been rented the tenants should have a rental contract with them. |
A letter of application should be written by the applicant to the licensed distributor (Aydem EDAS) with the below information included; |
a.) Tapu/Title Deed (island no., section no., plot no., etc.) of the place of usage and its address |
b.) The type of energy/power requested (If the applicant wants a private transformer installed the energy/power type is kVA, if they want to be provided by the AG the total project energy/power is kW.) |
c.) The intended usage of the facility or usage place requesting energy. |
d.) The duration for the temporary connection. |
2 - Documents Requested When Applying For A Connection Agreement: |
If the available distribution system meets the requested connection requirements; |
a.) Title Deed of the requested place |
b.) Certified Electricity Project Plans of the requested place |
c.) Occupancy permit for those that are within the zoning area, according to the 3194 numbered Zoning Law 30th,31st Articles |
d.) Ocupancy permit for those that are within established village areas and surroundings and fields, according to the 3194 numbered Zoning Law 27th,30th Articles |
e.) Occupancy permit given from the Public Works And Settlement Province Directorates for those that are outside developments and village areas |
f.) Permit document from the related authorities of the legislation for places that do not require a license |
g.) Meter Bill |
h.) Other documents that may be requested according to the relevant legislation |
i.) Electricity Project Plans and a permit for the intended use, for those that are requesting temporary connection from the distribution system, for a limited duration |